The Vizhinjam double-stack railway tunnel project may undergo a major redesign to carry double-stack containers to the port. The Keralam government is examining an upgrade to the proposed rail link from Balaramapuram.
The move follows the cancellation of an earlier engineering, procurement and construction (EPC) tender. That tender covered a conventional tunnel designed for single-stack containers.
According to sources, Konkan Railway Corporation Ltd (KRCL) is expected to issue a revised tender within one or two months. However, the government has not taken a final decision on the proposed upgrade.
Vizhinjam railway tunnel may get double-stack capacity
The previous Left Democratic Front (LDF) government had proposed a 10.7-km broad-gauge railway link. It would run underground from Balaramapuram to the Vizhinjam Port yard.
The tunnel alignment would pass beneath the Vizhinjam-Balaramapuram road. Furthermore, the project aims to provide direct rail connectivity to the Vizhinjam International Seaport.
Towards the end of its tenure, the LDF government had invited KRCL to execute the project. The corporation had earlier signed a memorandum of understanding with the state government.
However, the tender has since been cancelled. The revised proposal is expected to incorporate changes to the tunnel and associated rail infrastructure.
The upgrade could allow double-stack container movement. Consequently, it may improve the railway link’s capacity to transport cargo to the port.
Project cost could exceed Rs 2,000 crore
The proposed modifications are expected to increase the project’s estimated cost significantly.
The project was estimated to cost Rs 533.67 crore in 2016. However, the revised estimate has since increased to around Rs 1,500 crore.
The final cost could exceed Rs 2,000 crore upon completion, considering delays in execution. The proposed double-stack design could further affect the overall project expenditure.
Mission Samudra drives renewed focus on port connectivity
The newly formed United Democratic Front (UDF) government has begun examining the proposed upgrade. Chief Minister V.D. Satheesan also holds the Ports portfolio.
The government is pursuing Mission Samudra, a five-year maritime economic transformation initiative. It aims to integrate major and minor ports across Keralam.
The proposed railway link could strengthen Vizhinjam’s connectivity with cargo-producing regions. Moreover, it could help transport goods from different parts of the country to the port.
Vizhinjam handled record cargo volumes during its first year of commercial operations. Meanwhile, the port’s second development phase is expected to be completed by 2028.
The expansion is expected to increase the port’s handling capacity significantly.
Centre’s funding support remains a key issue
The state government’s ability to finance the entire railway link remains a concern. Keralam faces financial constraints, while other states could also benefit substantially from the connectivity.
A senior bureaucrat said the government had urged the Centre to bear the project’s cost. The state’s argument is that the rail link would primarily benefit states outside Keralam.
However, the funding arrangement remains unresolved. The government must also decide whether to adopt the double-stack design before KRCL issues the revised tender.