NBCC Supertech stalled projects face fresh uncertainty after the state-owned company offered to withdraw from their completion.
The National Buildings Construction Corporation told the Supreme Court on Monday that it would exit if homebuyers opposed its involvement.
Attorney General R Venkataramani, appearing for NBCC, said the company did not want to remain an unwanted participant. He also said its eight per cent project-cost fee followed government-fixed rates.
A bench comprising Chief Justice Surya Kant and Justices Joymalya Bagchi and V Mohana reserved its order. The court stressed the need for a clear execution plan to complete the stalled housing developments.
Homebuyers question NBCC’s progress on Supertech projects
The submission followed allegations from some homebuyers that NBCC had made no progress on the projects.
Senior advocate Menaka Guruswamy, representing around 6,000 homebuyers, said construction had not progressed across 16 towers in one project.
She also told the bench that many buyers had paid up to 90 per cent of their property costs. However, they were still waiting for possession.
The homebuyers urged the Supreme Court to appoint a court receiver. They argued that an effective mechanism was necessary to ensure completion.
Meanwhile, the court was informed that two companies had submitted proposals to invest funds. However, the bench questioned who would execute the construction work.
The judges also observed that NBCC does not directly execute projects itself. Furthermore, they made clear that homebuyers should not face any additional financial burden.
Venkataramani said NBCC was a public sector undertaking, not a real estate developer. The court said it would pass an appropriate order.
Supreme Court had directed NBCC to complete 16 projects
The Supreme Court had earlier upheld an NCLAT order directing NBCC to complete 16 of Supertech’s 30 housing projects.
On February 5, the apex court upheld the appellate tribunal’s directions. It also restrained tribunals and high courts from passing orders that could stall construction.
The court exercised its extraordinary powers under Article 142 of the Constitution. It upheld the NCLAT’s December 12, 2024 order in the interest of homebuyers.
The 16 projects comprise 49,748 homes across Uttar Pradesh, Uttarakhand, Haryana and Karnataka. Around 27,000 homebuyers are awaiting possession.
The court noted that Supertech had booked around 51,000 homes for delivery during 2010-12, according to homebuyers.
The NCLAT had directed NBCC to begin awarding construction contracts before March 31, 2025. It also required the company to complete the contract-awarding process within the following month.
Construction was scheduled to begin on May 1, 2025. However, the latest hearing has raised questions about execution and NBCC’s continued involvement.
NBCC had proposed a three-phase construction plan
NBCC had submitted a three-phase proposal to undertake the stalled developments. The plan covered projects across the National Capital Region, Dehradun and Bengaluru.
| Phase | Projects proposed |
|---|---|
| Phase 1 | Eco Village 2, Romano, Capetown, Czar Suites, Eco Village 3, Sports Village and Eco Citi |
| Phase 2 | Northeye, Upcountry, Eco Village 1, Meerut Sports City and Green Village |
| Phase 3 | Hilltown, Aravile, Rivercrest, Doon Square and Micasa |
The projects are located across Noida, Greater Noida, the Yamuna Expressway, Meerut, Gurugram, Rudrapur, Dehradun and Bengaluru.
The construction delays followed financial difficulties at Supertech. These developments led to insolvency proceedings against the real estate company in 2021.
Union Bank of India initiated insolvency proceedings under Section 7 of the Insolvency and Bankruptcy Code on March 20, 2021. The bank claimed dues exceeding Rs 431 crore as of January 31, 2021, along with accrued interest.
The Supreme Court’s forthcoming order will determine the next steps for the stalled developments. Meanwhile, thousands of homebuyers continue to await clarity on construction timelines and possession.