The Mumbai Metro Rail Corporation (MMRC) has started a socio-economic survey of around 800 buildings and structures for the proposed Metro Line 11 corridor.
The 17.5-km underground corridor will connect Wadala with the Gateway of India. The survey will document property details and assess the socio-economic profiles of occupants before construction begins.
MMRC has appointed Socioquest Solutions to conduct the exercise. The agency’s teams will carry out property measurements, photography and videography to establish baseline information.
Property owners and occupants have been asked to provide original documents and photocopies for verification by authorised survey officials.
Mumbai Metro Line 11: 14 stations planned
The proposed corridor will include 14 stations:
- Anik Depot
- Wadala Depot
- CGS Colony
- Ganesh Nagar
- BPT Hospital
- Shivdi
- Haji Bunder
- Darukhana
- Byculla
- Nagpada Junction
- Bhendi Bazaar
- CSMT Metro
- Horniman Circle
- Gateway of India
The Maharashtra government has allocated Rs 23,487 crore for the initial 16.5-km Metro 11 project in its 2026-27 state budget.
The larger corridor is expected to improve connectivity across central and south Mumbai. It will link residential and commercial areas with major transport hubs.
JICA and government agencies to fund the project
The project is expected to receive financial support from the Japan International Cooperation Agency (JICA).
JICA has offered a development assistance loan of 92.4 billion yen, equivalent to around Rs 5,500 crore, for the first phase up to Wadala.
Other proposed funding sources include the Brihanmumbai Municipal Corporation (Rs 2,411 crore) and Mumbai Port Authority (Rs 804 crore).
The state and central governments are expected to contribute Rs 3,137 crore each. Additionally, institutional loans will account for more than Rs 12,000 crore.
Metro Line 11 alignment and expansion plans
The broader Metro Line 11 plan envisages connectivity from Wadala to the Gateway of India through Nagpada and Crawford Market.
However, following a state government directive in March 2026, the Mumbai Metro Rail Corporation announced plans to develop the corridor as an independent line.
Under the revised alignment, the line will connect Bandra Terminus with the Gateway of India. It will pass through Dharavi, Wadala Depot, Sewri and CSMT.
The survey marks a preparatory step towards the proposed underground corridor. Its findings will help establish the baseline property and occupant details required ahead of project implementation.