Mumbai-Ahmedabad Bullet Train corridor has achieved a major milestone after engineers energised the Overhead Equipment (OHE) system on the Surat–Bilimora section on November 20, 2026. Specifically, the 50-km elevated alignment now carries active power across both Up and Down lines. Furthermore, Railway Minister Ashwini Vaishnaw announced that trial runs on this maiden stretch will begin in May 2027.
Electrification milestones and Surat-Bilimora infrastructure
The high-speed network features an advanced 2 × 25 kV Overhead Traction System supported by 14 Traction Substations (TSS) across 508 km. Specifically, the first substation at Bilimora in Gujarat’s Navsari district has finished key equipment installations and draws power from GETCO’s 220 kV Ambetha Grid Substation. Additionally, the Surat–Bilimora viaduct incorporates bridges across four rivers, a steel bridge over NH-53, and roughly 94,000 noise barriers.
| Corridor Milestone & Specification | Official Project Details |
| Total Corridor Length | 508 km (Mumbai to Ahmedabad) |
| First Trial Section | Surat–Bilimora (approx. 50 km elevated stretch) |
| OHE Energisation Date | November 20, 2026 |
| Signalling Completion Target | January 2027 |
| Trial Run Launch | May 2027 (using B-28 test train) |
| Commercial Launch Target | Last quarter of 2027 (Ahmedabad–Vapi phase) |
Meanwhile, authorities issued a strict public safety advisory warning citizens and workers to stay away from live overhead electrical installations.
Phased commissioning and B-28 train testing
Signalling work on the Surat–Bilimora section will conclude by January 2027, paving the way for high-speed tests using the B-28 train. Specifically, this specialised train operates at speeds up to 280 kmph and recently cleared rigorous pressure squeeze tests.

Moreover, construction work on the Maharashtra segment, including the undersea tunnel, continues advancing steadily. Therefore, as the Mumbai-Ahmedabad Bullet Train corridor transitions toward phased commissioning, officials will launch initial commercial services between Ahmedabad and Vapi in late 2027 before reaching Thane by 2029.