Mumbai-Ahmedabad bullet train trials are scheduled to begin in May 2027 on the 50-km Surat-Bilimora section in Gujarat. Railway Minister Ashwini Vaishnaw confirmed the timeline.
The section will become the first part of India’s inaugural high-speed rail corridor to undergo testing. Meanwhile, electrification work has been completed, while signalling-related work is expected to finish by January 2027.
Surat-Bilimora section completes electrification
The overhead electrification system on the elevated section was energised on November 20. The system covers both tracks and uses a 2×25 kV traction configuration.
Additionally, installation work at the Bilimora traction substation has been completed. The remaining signalling work is expected to conclude by January 2027.
The initial testing will use the B-28 train, which can operate at speeds of up to 280 kmph. The train has also cleared a squeeze test.
During this test, engineers subjected the train to pressure levels twice the atmospheric pressure expected during regular operations. The test demonstrated its ability to withstand demanding pressure conditions.
Bullet train project to open in phases
The Mumbai-Ahmedabad High-Speed Rail project will be commissioned in phases. Therefore, the Surat-Bilimora section will serve as the starting point for testing India’s first bullet train corridor.
Furthermore, the Ahmedabad-Vapi section is expected to be completed by the end of 2027. The service is targeted to reach Thane by 2029.
The project has also recorded progress on its civil infrastructure. As of September 2026, construction of 371 km of viaduct had been completed.
The phased rollout will allow testing and commissioning to progress across different sections. However, the stated timelines remain project targets.