Allahabad HC halts new construction on 236.87 acres of Jaypee Greens land

3 Min Read
allahabad-high-court-jaypee-greens-golf-course-construction

The Allahabad High Court has halted new construction across 236.87 acres allotted for the Jaypee Greens Golf Course in Greater Noida. The interim order also prohibits external development and the creation of third-party rights over the land.

A division bench of Justice Saumitra Dayal Singh and Justice Swarupama Chaturvedi passed the order on November 3. It was hearing a petition filed by the Jaypee Greens Golf Members Association against the Uttar Pradesh government and four other respondents.

The respondents include the Greater Noida Industrial Development Authority (GNIDA) and developers. The dispute centres on the permitted use of land under two identical lease deeds.

Court examines land-use restrictions under lease deeds

The lease agreements earmarked at least 193.85 acres of the 236.87-acre parcel for a golf course and clubhouse facilities. The remaining 43.02 acres were available for other permissible developments.

The petitioners challenged ongoing and proposed construction of villas, condominiums, apartments, hotels and a tennis academy. They also raised objections to other commercial and institutional buildings on land designated for the golf course.

The development authority and builders had argued their case before the court. These builders acquired rights from the original lessee, JP Associates Limited.

However, the bench rejected the prima facie claim that residential villas and apartments could qualify as “golf-related activities” under the master plan.

The court observed that the lease deeds indicated an intention to protect the minimum 193.85-acre area reserved for the golf course and clubhouse. It said the land-use restrictions required examination during the proceedings.

HC bars new construction and property transfers

Pending a final determination of what constitutes “golf-related activities”, the court imposed restrictions across the entire 236.87-acre parcel.

The order prohibits parties from initiating or continuing new construction and external development on any part of the land until the next hearing.

However, the court allowed internal development within specific constructed properties. Such work must proceed at the constructing party’s own risk and cost.

Additionally, the court prohibited the creation of third-party rights over the land and buildings constructed on it. This includes property sales, bookings and transfers.

The interim restrictions will remain in force until the matter comes up again. The court has scheduled the next hearing for December 7.

The proceedings will determine how the lease conditions apply to the disputed developments and which activities qualify as permissible golf-related uses.