Haryana RERA has ruled that homebuyers who retain their properties can claim interest for delayed possession. However, they cannot seek additional compensation for the same delay.
The authority’s adjudicating officer dismissed a complaint by two Delhi homebuyers seeking Rs 91 lakh from Anand Divine Developers. The complaint concerned delayed possession of a flat in Gurugram’s ATS Triumph project.
The order was passed on November 11 by adjudicating officer Rajender Kumar. He noted that the authority had already allowed the buyers’ delayed possession complaint on September 28, 2023.
That earlier order awarded interest at 10.7 per cent annually. Consequently, the officer held that the buyers could not claim additional damages for the same delay.
Buyers sought Rs 91 lakh in compensation
Dr Renu Srivastav and retired Colonel Dr Ashwini Goel booked unit 6031 in Tower 6. Their agreement with Anand Divine Developers was dated March 27, 2018.
The property was valued at Rs 1.9 crore. However, the buyers said they had paid approximately Rs 2.2 crore, including a Rs 1.56 crore Punjab National Bank loan.
They sought Rs 45.4 lakh with 18 per cent interest. Additionally, their claims included monthly rent of Rs 1.2 lakh and Rs 25 lakh for alleged harassment.
They also sought Rs 10 lakh each under Sections 72(a) and 14. The complaint included Rs 55,000 towards costs.
The buyers alleged several construction and finishing deficiencies. These included reduced carpet and terrace areas, missing imported wooden flooring and the absence of an electricity meter.
They also cited seepage and pending painting work. However, the adjudicating officer said these allegations had not been pleaded before the authority.
He referred to Rule 29(1), which requires the authority to establish a violation before entertaining such claims.
Compensation applies to buyers exiting projects
The officer cited Section 18(1) of the Real Estate (Regulation and Development) Act. He also referred to rulings by real estate appellate tribunals.
These included the Uttar Pradesh tribunal’s decision in Greater Noida Industrial Development Authority vs Ranjan Misra. He also cited the Haryana tribunal’s February 2026 ruling in Tata Housing vs Nitin Singhal.
Based on these precedents, the officer said compensation applies to buyers who withdraw from projects. Meanwhile, buyers who remain in projects can claim interest for every month of delay.
Allowing both interest and compensation for the same delay would be unwarranted, he held.
The developer had argued that it offered possession in May 2019. It also maintained that the buyers took physical possession on March 19, 2022.
The ruling reinforces the distinction between remedies available to buyers who retain their properties and those who exit delayed projects.