Adani Energy Solutions wins Rs 500 crore Bihar transmission project

3 Min Read
adani-energy-solutions-bihar-pirpainti-transmission-project

Adani Energy Solutions Limited (AESL) has won a transmission project in Bihar to evacuate power from the upcoming 2,400 MW Pirpainti power plant. The project will generate an annual tariff of Rs 500 crore once commissioned.

The company secured the project through the Tariff Based Competitive Bidding (TBCB) mechanism. It will strengthen Bihar’s transmission network and support the evacuation of electricity from Pirpainti in Bhagalpur district.

“The Pirpainti transmission scheme will create a robust evacuation system for 2,400 MW of generation capacity while strengthening Bihar’s transmission backbone. It will enhance grid reliability and resilience and help the state meet its growing power demand,” said Kandarp Patel, CEO of Adani Energy Solutions.

He added that the company remained committed to developing reliable transmission infrastructure to support India’s long-term energy security.

Project to add 881 circuit kilometres of transmission lines

AESL will implement the project through its special purpose vehicle, Vikramshila Power Transmission Ltd. The company expects to complete the project by the fourth quarter of 2028.

The infrastructure will add 881 circuit kilometres (ckm) of transmission lines and 3,160 MVA of transformation capacity to AESL’s portfolio.

Consequently, the company’s transmission network will increase to 30,683 ckm. Its total transformation capacity will reach 146,585 MVA.

The project will also strengthen power supply reliability across Bihar. Furthermore, it will improve the state’s ability to transmit electricity from the upcoming generation facility.

Four gas-insulated substations planned

The project includes four gas-insulated substations (GIS) at Jhanjharpur, Bethauli and Begusarai, along with associated transformation capacity.

The planned transmission infrastructure includes the following lines:

  • 400 kV double-circuit (DCDS) Pirpainti-Jhanjharpur line.
  • 400 kV DCDS Pirpainti-Begusarai line.
  • 400 kV DCDS Begusarai-Bakhtiyarpur line.
  • 220 kV DCDS Jhanjharpur-Bethauli line.
  • 220 kV DCDS Begusarai-Begusarai Town line.

Additionally, the project involves the line-in-line-out (LILO) arrangement of existing 220 kV and 132 kV transmission lines at Jhanjharpur. It will also include the construction of 400 kV line bays at Bakhtiyarpur grid substation.

AESL transmission capex reaches Rs 91,500 crore

With the latest win, AESL’s transmission capital expenditure pipeline has reached Rs 91,500 crore.

The company currently operates a transmission network of 30,683 ckm. Its transformation capacity stands at 146,585 MVA, making it India’s largest private-sector transmission company.

The Pirpainti project will expand this portfolio while supporting Bihar’s growing electricity requirements. Its completion is scheduled for the fourth quarter of 2028.